      Cool Trick: Determine Date After X Work Days
      
      Question: What is the expected completion date if a project starts on Jan 1st 2016 and is expected to take 60 working days to finish?
      
      Answer: The WORKDAY uses a start date, work days and optional holidays to calculate the expected completion date. Unfortunately, the 
      default result is formatted as a serial number...
      
      Hint: Change the cell format to Date
      